Related to https://communities.sas.com/t5/SAS-Enterprise-Guide/Changing-run-order-for-programs-in-process-flow/..., I have a problem.
In a slightly complicated project I have multiple serial processes which, although they could be parallelised, I want to keep separate to stop my head exploding.
Yesterday that's how they ran. This morning, seemingly without modification, one of the minor threads has changed direction. Instead of running 1-2-3-4, it's switched to 2-3-4-1. This is not quite what I wanted.
Process #1 sets two datasets together (I know I could use the append task, but that's not the solution I want). Previously I had the two sources (manually) linked to this process to show the precedence I wanted. If I de-link the first dataset it reverts to 1-2-3-4, and the whole project runs to completion with nary a warning.
Woohoo.
But why?
PS EG 7.13 (7.100.3.5408) (64-bit)