Hi Patrick, thank you for the reply. I will define steps to make things clearer. Flow is scheduled in Management console 9.2 to run daily at 6am. Flow has 16 file dependencies from a 3rd party provider At 6 am the flow triggers, the status of which is then 'running' The files arrive at 7 am The flow picks up the files and populates the data set. However, if the files do not arrive at the drop location the flow maintains a status of 'Running' at 6am the next day the following days flow will trigger at 6 am. Now there are 2 flows (today's and yesterdays) both with a status of 'running'. My worry is that when the files arrive both of these flows will run simultaneously and chew up the data. Thanks for the help, Regards, Jason