Hi,
How to write a weekly status/update report to your manager ? I know its not related to SAS, it is a general question.. sorry
I have to submit weekly report to my manager regarding work progress, I am submitting all common things ... Can any one give me one whole format so I can get a perfect idea about it, what to add on it and how its look like.... (I am sending an email to them)..
Thank you
- Ranny
- Mark as New
- Bookmark
- Subscribe
- Mute
- RSS Feed
- Permalink
- Report Inappropriate Content
This may seem like the wrong order but a busy manager will appreciate putting the most important first
Action you require to take - none
Issues we need to discuss - none
Blockers hindering progress - none
Decisions made - none
Upcoming leave - none
Project milestones reached - none
Project Progress
- Phase 1 description deadline 80%
- Phase 2 description deadline 20%
- Phase 3 description deadline (not started)
Richard in Oz
- Mark as New
- Bookmark
- Subscribe
- Mute
- RSS Feed
- Permalink
- Report Inappropriate Content
I would add that the report should contain no surprises.
If there is anything that a manager needs to know that requires their action or decision, it should be raised immediately, and not wait for the weekly report.
Richard in Oz