data have;

input DOW $ HOLIDAY_FLG $ DATE DATE9.;

FORMAT DATE DATE9.;

DATALINES;

 

 

MON Y 1JAN2018

TUE N 2JAN2018

WED N 3JAN2018

THU N 4JAN2018

FRI N 5JAN2018

SAT N 6JAN2018

 

notice that 1jan2018 is a holiday.  If I encounter a holiday on a Monday I want to add a field called date_flg and say

MON Y 1JAN2018    4

TUE N 2JAN2018     2

WED N 3JAN2018    2

THU N 4JAN2018     2

FRI N 5JAN2018      2

;

RUN;

If Mon is a holiday I want the date_flg to equal 4, the remaining days of the week should equal 2

If Mon is NOT a holiday I want the date_flg to equal 3 and the remaining days of the week should equal 1 

I tried the lag function without success.  Essentially I am attempting to evaluate previous row and populate based on this.  Any ideas

1 REPLY 1
ChrisNZ
Tourmaline | Level 20

Like this?

data WANT;
  retain MON_IS_HOL;
  set HAVE;
  if DOW = 'MON' then MON_IS_HOL=(HOLIDAY_FLG='Y');
  if DOW = 'MON' then DATE_FLG=3+MON_IS_HOL;
  else                DATE_FLG=1+MON_IS_HOL;
run;

 

DOW HOLIDAY_FLG DATE DATE_FLG
MON Y 01JAN2018 4
TUE N 02JAN2018 2
WED N 03JAN2018 2
THU N 04JAN2018 2
FRI N 05JAN2018 2
SAT N 06JAN2018 2

SAS Innovate 2025: Save the Date

 SAS Innovate 2025 is scheduled for May 6-9 in Orlando, FL. Sign up to be first to learn about the agenda and registration!

Save the date!

How to Concatenate Values

Learn how use the CAT functions in SAS to join values from multiple variables into a single value.

Find more tutorials on the SAS Users YouTube channel.

SAS Training: Just a Click Away

 Ready to level-up your skills? Choose your own adventure.

Browse our catalog!

Discussion stats
  • 1 reply
  • 557 views
  • 0 likes
  • 2 in conversation