Hello,

 

Instead of generating forecast values for a time series by using the parameter estimates produced by the previous ESTIMATE statement as in the forecast statement in PROC ARIMA, I want to generate forecast values for a time series by user supplied parameter estimates.

 

Basically I want to perturb the parameter estimates produced by the previous ESTIMATE statement by adding a random noise to it and then use them to generate forecast values.

 

Is there any way I could accomplish this?

 

Thanks

 

P.S: Please tell me if any part of the question is unclear.

1 ACCEPTED SOLUTION

Accepted Solutions
rselukar
SAS Employee

You can use the ESTIMATE statement options such as  AR=, MA=, ... and NOEST to fix the parameter values to your desired settings.  See the "Options to Specify Parameter Values" section of the ESTIMATE statement documentation.

View solution in original post

1 REPLY 1
rselukar
SAS Employee

You can use the ESTIMATE statement options such as  AR=, MA=, ... and NOEST to fix the parameter values to your desired settings.  See the "Options to Specify Parameter Values" section of the ESTIMATE statement documentation.

Ready to join fellow brilliant minds for the SAS Hackathon?

Build your skills. Make connections. Enjoy creative freedom. Maybe change the world. Registration is now open through August 30th. Visit the SAS Hackathon homepage.

Register today!
Multiple Linear Regression in SAS

Learn how to run multiple linear regression models with and without interactions, presented by SAS user Alex Chaplin.

Find more tutorials on the SAS Users YouTube channel.

Discussion stats
  • 1 reply
  • 1158 views
  • 0 likes
  • 2 in conversation