I have a 3 Jobs running parallel inside a Job Reference in a Process Flow. Each of the Job strings end with an expression test that results in a raiseevent.  In the process flow I have 3 listeners chained ( assuming that creates an AND requirement to continue)

 

I have similar structures for other files but they only have a single or double Event listener.  THESE WORK and the process continues as it should but when I have 3 it stops at the 3rd one and doesn't appear to get the event

 

 

Is this possible or is there a limit of 2. Am I using the listeners incorrectly ?

 

 

Goal :   Check the file structures and that there is files to process .   If pass continue on to the actual ETL portion of the process without stopping the other branches of the process

1 ACCEPTED SOLUTION

Accepted Solutions
VincentRejany
SAS Employee

If the use case is to start a main job checking if some conditions are met, I don't think that listeners are mandatory. Listeners are designed for running a specific process upon an event, like a try/catch.

For your case, I will monitor that each sub succeeds, and if all of them are ok I will run the main one. put a quick example in attachment.

 

Hope that helps

View solution in original post

5 REPLIES 5
VincentRejany
SAS Employee

Hi

 

I don’t think there is any limit for events.

However I do think the design is important. Is the attachment containing an example of your job?

If I understand well 3 conditions have to be met for the ELT job to be started right?

 

Vincent

Rcflyboyjr
Calcite | Level 5

Vincent Thank you for responding .. attached is a simpler job example .. But yes that is the essence of it. I have 2 or more events connecting to either an IF node or an expression . when ALL listeners occur then execute the job on other side.

 

I cant figure out how to accept a success (Continue Processing) from the Listeners.

Rcflyboyjr
Calcite | Level 5

sorry error when attach .. here it is zipped

VincentRejany
SAS Employee

If the use case is to start a main job checking if some conditions are met, I don't think that listeners are mandatory. Listeners are designed for running a specific process upon an event, like a try/catch.

For your case, I will monitor that each sub succeeds, and if all of them are ok I will run the main one. put a quick example in attachment.

 

Hope that helps

Rcflyboyjr
Calcite | Level 5

That's perfect Thank you that will work perfectly, I understand it AND you introduced Get/Set and how to actually use the IF node. this was VERY helpful

sas-innovate-wordmark-2025-midnight.png

Register Today!

Join us for SAS Innovate 2025, our biggest and most exciting global event of the year, in Orlando, FL, from May 6-9. Sign up by March 14 for just $795.


Register now!

How to connect to databases in SAS Viya

Need to connect to databases in SAS Viya? SAS’ David Ghan shows you two methods – via SAS/ACCESS LIBNAME and SAS Data Connector SASLIBS – in this video.

Find more tutorials on the SAS Users YouTube channel.

Discussion stats
  • 5 replies