I need some advice. I am using 14.2 I have a scheduling problem which is solved using Proc CLP. It utilises the ACTDATA, RESDATA data sets. I need to add a number of constraints to when resources are available as described below. Scenario 1 Resource A is not available on day 2 and therefore Resource A cannot be assigned to any activity that is scheduled over that period. Scenario 2. The resources assigned for use on Activity A must also be assigned to Activity B. Using the data below, if the resource VANCOVER is assigned to Activity AA2, then resource VANCOVER must also be assigned to activity AB2. ACTIVITY DATA ACTIVITY SUCCESSOR DURATION RESOURCE QTY AA1 AA3 12 CANADA 1 AA2 AA3 20 UK 1 AA3 AB2 30 CANADA 1 AA4 AB3 30 CANADA 1 AB2 AB3 20 CANADA 1 AB3 10 UK 1 RESOURCE DATA RESOURCE CAPACITY POOL SUBQTY LONDON 1 UK 1 EDINBURGH 1 UK 1 VANCOVER 1 CANADA 1 CALGARY 1 CANADA 1 How can I add these constraints to the problem using Proc CLP or should the model be reworked using Proc OPTMODEL.