Exploring, predicting and reporting with SAS Visual Analytics and SAS Visual Statistics

schedule the running of a SAS VA report

Accepted Solution Solved
Reply
Contributor BLE
Contributor
Posts: 35
Accepted Solution

schedule the running of a SAS VA report

I know how to set up a schedule for the running of a SAS VA query using Data Preparation and the Scheduler icon (looks like a clock), but I need to schedule the running of a report, not a query.  Is that possible? If yes, please share the path - which screen gets you to the scheduler in the design report tab?  I am working with SAS VA 7.4


Accepted Solutions
Solution
‎12-04-2017 02:32 PM
SAS Super FREQ
Posts: 586

Re: schedule the running of a SAS VA report

When the user clicks the link in the email, the most current copy of the report is displayed.

 

However, the PDF in the distributed email is a static view that reflects the state of the report at the time that the PDF was generated. You cannot exclude the PDF from the distributed email. However, if the PDF is always greater than 1 mg, then you might be able to modify the property that limits the size of the PDF so that Visual Analytics strips the file from the email. The va.distribution.email.attachment.mb property is discussed in the Visual Analytics Admin Guide under Suite-Level Properties..

View solution in original post


All Replies
SAS Super FREQ
Posts: 586

Re: schedule the running of a SAS VA report

You can schedule report distribution via email to a specified list of recipients. That is the only scheduling available for reports. In Visual Analytics Designer, select File > Distribute. You first create a job, and then you set your time-event for distribution.

 

See Distributing Reports in the SAS Visual Analytics User's Guide.

 

Contributor BLE
Contributor
Posts: 35

Re: schedule the running of a SAS VA report

Posted in reply to Madelyn_SAS

Will the report be run freshly when the recipient of the email clicks on the link to the report?

 

Solution
‎12-04-2017 02:32 PM
SAS Super FREQ
Posts: 586

Re: schedule the running of a SAS VA report

When the user clicks the link in the email, the most current copy of the report is displayed.

 

However, the PDF in the distributed email is a static view that reflects the state of the report at the time that the PDF was generated. You cannot exclude the PDF from the distributed email. However, if the PDF is always greater than 1 mg, then you might be able to modify the property that limits the size of the PDF so that Visual Analytics strips the file from the email. The va.distribution.email.attachment.mb property is discussed in the Visual Analytics Admin Guide under Suite-Level Properties..

☑ This topic is solved.

Need further help from the community? Please ask a new question.

Discussion stats
  • 3 replies
  • 288 views
  • 0 likes