I wrote a code that calculates eight lags and eight leads for each macro variable in my list and then uses OLS and WLS to calculate R-squared. But my code is not well written since for each lag and lead I had to copy-paste the same procedure and then manually modify it for the corresponding lag or lead. Is there any way I can create a loop for lags and leads, say, for i = 1:8, create lags, or for j =1:8, create leads and then run the following steps blah-blah-blah.

 

Also, once I created lags and leads for each macro variable, I have a column lag_1 or lead_1 and row that shows the name of the macrov variable.  But if later on I need to use, say BBB_lag_1 in my OLS regression, I don't know how to identify that specific cell. Does anyone know what the best way to assign names for each variable in column lag_1 that corresponds to the name of the appropriate row (say, BBB) and then attach the name of the appropriate column (say, lag_1). I am sorry for my English. It is probably confusing.

 

The code is attached.

 

libname UB 'blah-blah-blah';

%let macro = ub.macro_lgd_f1f8_LZ_YT;

%let list =

rGDP_grw

rGDP_grw_yoy

nGDP_grw

nGDP_grw_yoy

rDPI_grw

rDPI_grw_yoy

nDPI_grw

nDPI_grw_yoy

 

 

ata ub.laglead;

set &macro;

array var_list(*) &list;

do i = 1 to dim(var_list);

variable = vname(var_list(i));

value = var_list(i);

output;

end;

keep Date AVG_LGD variable value ;

run;

proc sort data=ub.laglead;

by variable date;

run;

* Create 8 lags and 8 leads of each macro variable in the list;

data ub.laglead;

set ub.laglead;

by variable;

lag_1=ifn(first.variable=0,lag(value),.);

lag_2=ifn(lag2(variable)=variable, lag2(value),.);

lag_3=ifn(lag3(variable)=variable, lag3(value),.);

lag_4=ifn(lag4(variable)=variable, lag4(value),.);

lag_5=ifn(lag5(variable)=variable, lag5(value),.);

lag_6=ifn(lag6(variable)=variable, lag6(value),.);

lag_7=ifn(lag7(variable)=variable, lag7(value),.);

lag_8=ifn(lag8(variable)=variable, lag8(value),.);

if eof1=0 then set ub.laglead (firstobs=2 keep=value rename=(value=lead_1)) end=eof1;

if last.variable then lead_1 =.;

if eof2=0 then set ub.laglead (firstobs=3 keep=variable value rename=(variable=variable3 value=lead_2)) end=eof2;

if variable3^= variable then lead_2 =.;

drop variable3;

if eof3=0 then set ub.laglead (firstobs=4 keep=variable value rename=(variable=variable4 value=lead_3)) end=eof3;

if variable4^= variable then lead_3 =.;

drop variable4;

if eof4=0 then set ub.laglead (firstobs=5 keep=variable value rename=(variable=variable5 value=lead_4)) end=eof4;

if variable5^= variable then lead_4 =.;

drop variable5;

if eof5=0 then set ub.laglead (firstobs=6 keep=variable value rename=(variable=variable6 value=lead_5)) end=eof5;

if variable6^= variable then lead_5 =.;

drop variable6;

if eof6=0 then set ub.laglead (firstobs=7 keep=variable value rename=(variable=variable7 value=lead_6)) end=eof6;

if variable7^= variable then lead_6 =.;

drop variable7;

if eof7=0 then set ub.laglead (firstobs=8 keep=variable value rename=(variable=variable8 value=lead_7)) end=eof7;

if variable8^= variable then lead_7 =.;

drop variable8;

if eof8=0 then set ub.laglead (firstobs=9 keep=variable value rename=(variable=variable9 value=lead_8)) end=eof8;

if variable9^= variable then lead_8 =.;

drop variable9;

run;

*Calculate Rsquared using ordinary OLS;

** Run an OLS regression where the dependent variable is LGD and independent varialbe (one at a time) macroeconomic variable;

proc reg data=ub.laglead outest=ub.OLS_est_value tableout;

by variable;

model AVG_LGD=value/selection=rsquare b;

output out=ub.OLS_pred_value residual=OLS_residual_value predicted=OLS_predicted_value;

run;

*ods graphics off;

proc print data=ub.OLS_est_value;

run;

****************************EIGHT LAGS *****************************;

* Lag 1;

*ods graphics on;

proc reg data=ub.laglead outest=ub.OLS_est_lag_1 tableout;

by variable;

model AVG_LGD=lag_1/selection=rsquare b;

output out=ub.OLS_pred_lag1 residual=OLS_residual_lag1 predicted=OLS_predicted_lag1;

run;

*ods graphics off;

proc print data=ub.OLS_est_lag_1;

run;

* Lag 2;

proc reg data=ub.laglead outest=ub.OLS_est_lag_2 tableout;

by variable;

model AVG_LGD=lag_2/selection=rsquare b;

output out=ub.OLS_pred_lag2 residual=OLS_residual_lag2 predicted=OLS_predicted_lag2;

run;

*ods graphics off;

proc print data=ub.OLS_est_lag_2;

run;

* Lag 3;

proc reg data=ub.laglead outest=ub.OLS_est_lag_3 tableout;

by variable;

model AVG_LGD=lag_3/selection=rsquare b;

output out=ub.OLS_pred_lag3 residual=OLS_residual_lag3 predicted=OLS_predicted_lag3;

run;

*ods graphics off;

proc print data=ub.OLS_est_lag_3;

run;

* Lag 4;

proc reg data=ub.laglead outest=ub.OLS_est_lag_4 tableout;

by variable;

model AVG_LGD=lag_4/selection=rsquare b;

output out=ub.OLS_pred_lag4 residual=OLS_residual_lag4 predicted=OLS_predicted_lag4;

run;

*ods graphics off;

proc print data=ub.OLS_est_lag_4;

run;

* Lag 5;

proc reg data=ub.laglead outest=ub.OLS_est_lag_5 tableout;

by variable;

model AVG_LGD=lag_5/selection=rsquare b;

output out=ub.OLS_pred_lag5 residual=OLS_residual_lag5 predicted=OLS_predicted_lag5;

run;

*ods graphics off;

proc print data=ub.OLS_est_lag_5;

run;

* Lag 6;

proc reg data=ub.laglead outest=ub.OLS_est_lag_6 tableout;

by variable;

model AVG_LGD=lag_6/selection=rsquare b;

output out=ub.OLS_pred_lag6 residual=OLS_residual_lag6 predicted=OLS_predicted_lag6;

run;

*ods graphics off;

proc print data=ub.OLS_est_lag_6;

run;

* Lag 7;

proc reg data=ub.laglead outest=ub.OLS_est_lag_7 tableout;

by variable;

model AVG_LGD=lag_7/selection=rsquare b;

output out=ub.OLS_pred_lag7 residual=OLS_residual_lag7 predicted=OLS_predicted_lag7;

run;

*ods graphics off;

proc print data=ub.OLS_est_lag_7;

run;

* Lag 8;

proc reg data=ub.laglead outest=ub.OLS_est_lag_8 tableout;

by variable;

model AVG_LGD=lag_8/selection=rsquare b;

output out=ub.OLS_pred_lag8 residual=OLS_residual_lag8 predicted=OLS_predicted_lag8;

run;

*ods graphics off;

proc print data=ub.OLS_est_lag_8;

run;

****************************EIGHT LEADS *****************************;

* Lead 1;

*ods graphics on;

proc reg data=ub.laglead outest=ub.OLS_est_lead_1 tableout;

by variable;

model AVG_LGD=lead_1/selection=rsquare b;

output out=ub.OLS_pred_lead1 residual=OLS_residual_lead1 predicted=OLS_predicted_lead1;

run;

*ods graphics off;

proc print data=ub.OLS_est_lead_1;

run;

* Lead 2;

proc reg data=ub.laglead outest=ub.OLS_est_lead_2 tableout;

by variable;

model AVG_LGD=lead_2/selection=rsquare b;

output out=ub.OLS_pred_lead2 residual=OLS_residual_lead2 predicted=OLS_predicted_lead2;

run;

*ods graphics off;

proc print data=ub.OLS_est_lead_2;

run;

* Lead 3;

proc reg data=ub.laglead outest=ub.OLS_est_lead_3 tableout;

by variable;

model AVG_LGD=lead_3/selection=rsquare b;

output out=ub.OLS_pred_lead3 residual=OLS_residual_lead3 predicted=OLS_predicted_lead3;

run;

*ods graphics off;

proc print data=ub.OLS_est_lead_3;

run;

* Lead 4;

proc reg data=ub.laglead outest=ub.OLS_est_lead_4 tableout;

by variable;

model AVG_LGD=lead_4/selection=rsquare b;

output out=ub.OLS_pred_lead4 residual=OLS_residual_lead4 predicted=OLS_predicted_lead4;

run;

*ods graphics off;

proc print data=ub.OLS_est_lead_4;

run;

* Lead 5;

proc reg data=ub.laglead outest=ub.OLS_est_lead_5 tableout;

by variable;

model AVG_LGD=lead_5/selection=rsquare b;

output out=ub.OLS_pred_lead5 residual=OLS_residual_lead5 predicted=OLS_predicted_lead5;

run;

*ods graphics off;

proc print data=ub.OLS_est_lead_5;

run;

* Lead 6;

proc reg data=ub.laglead outest=ub.OLS_est_lead_6 tableout;

by variable;

model AVG_LGD=lead_6/selection=rsquare b;

output out=ub.OLS_pred_lead6 residual=OLS_residual_lead6 predicted=OLS_predicted_lead6;

run;

*ods graphics off;

proc print data=ub.OLS_est_lead_6;

run;

* Lead 7;

proc reg data=ub.laglead outest=ub.OLS_est_lead_7 tableout;

by variable;

model AVG_LGD=lead_7/selection=rsquare b;

output out=ub.OLS_pred_lead7 residual=OLS_residual_lead7 predicted=OLS_predicted_lead7;

run;

*ods graphics off;

proc print data=ub.OLS_est_lead_7;

run;

* Lead 8;

proc reg data=ub.laglead outest=ub.OLS_est_lead_8 tableout;

by variable;

model AVG_LGD=lead_8/selection=rsquare b;

output out=ub.OLS_pred_lead8 residual=OLS_residual_lead8 predicted=OLS_predicted_lead8;

run;

*ods graphics off;

proc print data=ub.OLS_est_lead_8;

run;

1 ACCEPTED SOLUTION

Accepted Solutions
Ksharp
Super User

You are checking Autocorrelation . Check proc autoreg :

proc autoreg data=have;
model AVG_LGD= /dw=5 dwprob; /* Lag 1 2 3 4 5*/
run; 

View solution in original post

4 REPLIES 4
Reeza
Super User

Do you have a license for SAS/ETS?

 

Proc setinit;run;
yelena
Fluorite | Level 6

Dear Reeza,

Thank you for your response. Yes, I do.

Yelena

 

Reeza
Super User

In addition, to @Ksharp correct solution, which requires SAS/ETS, you can use proc expand to calculate lead/lag variables. See the documentation for examples. 

 

Just as an FYI. 

Ksharp
Super User

You are checking Autocorrelation . Check proc autoreg :

proc autoreg data=have;
model AVG_LGD= /dw=5 dwprob; /* Lag 1 2 3 4 5*/
run; 

sas-innovate-2024.png

Join us for SAS Innovate April 16-19 at the Aria in Las Vegas. Bring the team and save big with our group pricing for a limited time only.

Pre-conference courses and tutorials are filling up fast and are always a sellout. Register today to reserve your seat.

 

Register now!

What is ANOVA?

ANOVA, or Analysis Of Variance, is used to compare the averages or means of two or more populations to better understand how they differ. Watch this tutorial for more.

Find more tutorials on the SAS Users YouTube channel.

Discussion stats
  • 4 replies
  • 1542 views
  • 2 likes
  • 3 in conversation