Hello all!

I'm using LSF JobScheduler. I describe the flow in the SMC editor. How do I specify that the flow should stop its execution if a error was completed at least one job?

Yuri.
Super Contributor
Posts: 356

Re: Scheduling with SMC 9.2

In SMC One way is through the job dependancies in the flow. and/or using the attributes tab in the properties of the flow.

Barry
New Contributor
Posts: 4

Re: Scheduling with SMC 9.2

Posted in reply to twocanbazza
On the Attributes tab is not such a possibility ((
But in "Flow Editor" have this option. In 9.2, Flow editor replaced by SMC.
Super Contributor
Posts: 356

Re: Scheduling with SMC 9.2

But in "Flow Editor" have this option. In 9.2, Flow editor replaced by SMC"

???
New Contributor
Posts: 4

Re: Scheduling with SMC 9.2

Posted in reply to twocanbazza
Flow editor has this option.
In the SMC 9.2 is not an option. Message was edited by: rusyba
Super Contributor
Posts: 356

Re: Scheduling with SMC 9.2

Sorry, I am now a little confused.

What is "Flow Editor"? Are you talking about "Flow Manager".

I am using 9.2 and in SMC I have the option I mentioned, visable on the attributes tab of the properties of the Flow. Am mistaken on what you are asking for?