PROC SHEWART graphical options

Hello all- 

 

Have a couple of questions about graphical output in respects to proc shewart- 

 

Code is as follows-straight forward

proc shewhart data=togr (where=(UNIT="xxxx"));
Pchart pct_compl * date/ NOLIMIT0 NOLIMIT1 subgroupn =1 markers tests = 1 to 8 VFORMAT=percent10. ;

label pct_compl = 'percent Compliance'
date = 'Date' ;
run;

 

So two things I would like to do- 

1) change the vertical axis format to percent. Vformat seems not to adhere to my demands (in graph below-no title)

2) How do I get the labels in the graph (labeled Process47-from SAS) so it outputs the meaning of Tests in the legend 

 

Thank you 

 

Lawrence 

 SAS_OUTPUT.png

PCHART.png

 
Regular Contributor
Regular Contributor
Posts: 159

Re: PROC SHEWART graphical options

Ok ignore #2 -I just needed to rest the ods graphics

 