Desktop productivity for business analysts and programmers

Scheduling with condition processing Eg 4.2

Reply
New Contributor
Posts: 3

Scheduling with condition processing Eg 4.2

Hi,

I've some problems with scheduling an Eg 4.2 project. Without the condition processing it was working fine.

I added a condition that is dependent on the prompt, it checks if the data of yesterday (default parameter) is in the dataset.

If not; sent an email of it is then start the rest of the process.

When I perform the query in EG it works...when scheduled not!

Community Manager
Posts: 2,692

Re: Scheduling with condition processing Eg 4.2

Hi, this is a known problem and has been tracked as a defect.  And it looks we have a hotfix for it in SAS Enterprise Guide 4.3.

See:

http://support.sas.com/kb/42/975.html

The note includes links to the hotfix.


Chris

Ask a Question
Discussion stats
  • 1 reply
  • 94 views
  • 0 likes
  • 2 in conversation